A project has five activities as follows:
Activity: A, B, C, D, E
Preceding Activity: -, -, B, C, B
Duration (Days): 4, 8, 5, 9, 5
a) Find critical path using EST's / LST's
b) Calculate the floats of the network.

Respuesta :

Otras preguntas

What does a my mitochondria do in a plant cell
what is a lotus plant
Why did the British win the battle of Saratoga
To write the polynomial 5x^4+8x^5-2x+3 in standard form, which term is the leading term? A. The constant term B. The quintic term C. The quartic term D. The l
Two identical billiard balls are rolling toward each other at the same speed. What will be true after they collide head–on?
AP Psych An understanding of the spacing effect provides insight into effective strategies for... A) rehearsal B) chunking C) repression D) automatic processing
Is "Her brothers grew up and moved away." A compound sentence
13. Simplify: (-5-√3)^2
did the printing press preserve the past or invent the future? i need help please
Anna is drawing the midsegment of angle LNM that is parallel to line LN What are the coordinates of the endpoints of the midsegment?