The Project Evaluation and Review Technique (PERT) was developed as a means of scheduling and controlling projects with constant activity times. Group of answer choices False True

Respuesta :

topeadeniran2 topeadeniran2
  • 16-08-2020

Answer: False

Explanation:

The Program Evaluation and Review Technique (PERT) is used to know the schedule tasks and also know the critical path variation. It is useful to know the length of time that'll be needed for the completion of every task and how it relates to others in order to know the entire time needed to complete the particular project.

The Project Evaluation and Review Technique (PERT) is not a means of scheduling and controlling projects with constant activity times. The activity time normally varies.

Answer Link

Otras preguntas

PLZ ANSWER FAST! BRAINLIST FOR CORRECT ANSWER! "The country was wooded everywhere except at the bottom of the valley to the northward, where there was a small n
Odell walk 7.35 Mi his brother Darnell walk 2.3miles as much as Odell how many miles did Darnell walk
84 is 60% of what number?
please help would mean a lot :?)
Could someone explain the answer? GIVING 12 POINTS
what is the distance between -7 and -2. HELLLLPPPPPPPPPPP
Colton can rake 79/10 bags of leaves each hour. How many bags of leaves will colton rake and fill in 6 hours. I need to know the steps to answering this.
This is hard for me please
Nancy drove from New York to Boston, a distance of 1144.97 km. She drove with a friend for the first 711.5 km, and then by herself for the remaining distance.
How do you write an equation in slope intercept when given the slope and a point?