12 workers can do a peice of work in 20 days. How many workers should be added to complete work in 16 days?​

Respuesta :

atchleyamirah69
atchleyamirah69 atchleyamirah69
  • 01-04-2021
3 workers

if 12 workers can do a piece of work in 20 days, then one person can do it in 240 days. 240/16 is 15. That is the number of workers that you need in total to it in 16 days. Since the question ask how many more workers,
15 - 12 = 3 more workers.
Answer Link

Otras preguntas

Which of the following types of tracts are used to conduct nerve impulses between gyri within the same cerebral hemisphere? a. Mammillothalamic tracts b. Stria
What is the 2nd coordinate?
have some fun,,lets play dirty truth and dare in this meet,,boys and girls,,?​​
The length of a rectangle is 4yd longer than its width. If the perimeter of the rectangle is 40yd , find its area.
has honda made enough improvements to their1.5 liter 4 cyl. turbo engine so that its reliability matches that which honda engines are known for___
Most business leaders believe that their primary responsibilities to their employees include which of the following
reddit feel super hungry but im not supposed to eat after midnight because I have anesthetic what should I do
Which of the following tables may represent a linear function?
What are stage directions meaning?
12 Sketch the graphs of the following equations on the same Cartesian coordinate plane a) 2y + 7 = 3x b) 1/2x + 4y = 6