Mr. Kumar is getting his house renovated. 1/5 th of the work has been completed in 2 months. How much time will it take for the entire work to be completed?

Respuesta :

liam2747
liam2747 liam2747
  • 02-05-2021

Answer:

10 months

Step-by-step explanation:

If it takes 2 months to do 1/5th, it will take 4 months to do 2/5, 6 months to do 3/5, 8 months to do 4/5, and 10 months to do 5/5 or in other words the whole thing.

Answer Link

Otras preguntas

4842 divided by 93 with remainder
Worth more Points!!!!
When building a team which profession is most similar to that of the team leader?
When a pathogen infects a cell what kind of white blood cells are activated describe their appearance?
PLEASE PLEASE ANSWER! Read the excerpt below and answer the question. BRACK: What bonnet were you talking about? HEDDA: Oh, it was a little episode with Miss T
Whether you operate your business from a small office at home or in a large plant environment, it's still referred to as your A. operating plant. B. market. C.
who was caesar chavez
1. Disposable Income Consumer Spending $10,000 $7,500 $12,000 $8,500 What is the expenditure multiplier according
The answer I got was x is less than or equal to 2 but I’m not sure if I’m correct
Why were the Aztecs civilized?