momlover784
momlover784 momlover784
  • 13-08-2021
  • Mathematics
contestada

if 16 men can finish to contruct a bulding in 40 days how manny more men are needed to finish the contruction in 32 days​

Respuesta :

ALWAYSSINGLEME
ALWAYSSINGLEME ALWAYSSINGLEME
  • 13-08-2021

Answer:

20 mens are needed to contruct a building in 32 days.

Answer Link

Otras preguntas

(1) Express 0.35 bar in p/q form​
Select the correct answer. What is the value of a in this linear system? a+b+c= 62 a-b 12 2a+b+c= 92 OA. 30 OB. 18 C. 14 D. 26 فن
statistical question box for numbers 4,7,7,9,9,10,13,13,15,16
ventajas y desventajas de la extracción minera en el ecuador
Use the following image to answer the question: The image depicts a series of steps in a diagram. At the top of the diagram is a large horizontal box labeled D.
which two slave holding states donated the land that would be used to form DC
Which term is on both sides of the equal sign? Since it’s on both sides of the equal sign, you can cancel it out. What is the expression after canceling out the
Huh I don’t understand this. Monstrousity
If a victim is coughing forcefully... A) perform CPR immediately. B) encourage continued coughing to clear the object. C) lay the victim on his/her side. D) per
Outline four ways in which people experience discrimination