If it takes 4 workers 21 hours to paint how many hours will it take 12 workers?

Respuesta :

m11233982
m11233982 m11233982
  • 12-09-2022

Answer:

63 hours

Step-by-step explanation:

4 workers = 21 hours

12 workers = g

[tex] \frac{21}{4} \times 12 \\ = 63hours[/tex]

Answer Link

Otras preguntas

How do I graph f(x)= -cos(x-pi)?
A basketball player achieves a hang time of 0.773 s in dunking the ball. What vertical height will he attain? The acceleration of gravity is 9.8 m/s^2 .
What does it mean when sperm can't penetrate the eggs
If you know two points on a line, how can you find the rate of change of the variables being graphed?
while your finger is still pushing the coin, there are four forces acting on the coin: what are they?
plz help me solve this question how many remain when 87 is divided by 9
1. Compare the location of electrons in an atom based on Bohr's theory with the location of electrons in an atom based on the current atomic theory. 2. Rutherf
how can you tell the difference between additive comparison and multiplication comparison
What is the fraction ten fourteenths in its simplest form?
2b^2+4b–2=0 what is the answer?