If it takes 100 minutes to complete a circuit, demand at the next work center is 5 parts per minute, and a kanban container holds 20 parts, how many containers are required?

Respuesta :

miamonroe56
miamonroe56 miamonroe56
  • 02-06-2017
5 times 100 = 500
500 divided by 20 = 25
25 containers
Answer Link

Otras preguntas

Teens are at a higher risk of using illegal drugs because
A pendulum is made of a 250 g metal ball suspended 50.0 cm below a support by a string. The ball is moved sideways along the swing arc so that it is 3.0 cm high
write an algebraic expression to represent b less than 50
What was Galens area of expertise
China was first introduced to European culture by Portugal China was first introduced to European culture by Portugal a. True b. False?
which of the following describes the effect of boiling and freezing
please help me on this
the first atomoic bomb used in warfare dropped o the city of?
Evaluate each permutation 7p3
Choose the correct simplification of the expression the quantity a to the 2nd power over b to the 3rd power all raised to the 4th power. a to the 6th power over